Posted an entry on Glen-L Hot Rod
We applied the last three epoxy barrier coats on Saturday
-
Posted an entry on Glen-L Hot Rod
An extra layer of cloth was applied to the keel and the bow area
-
Posted an entry on Glen-L Hot Rod
The shaft tube was epoxied and trimmed
-
Posted an entry on Glen-L Hot Rod
We're applying the fiberglass cloth using the 'dry method'
-
Posted an entry on Glen-L Hot Rod
Took Friday off to feather the overlaps and sand the hull with 40 grit sandpaper
-
Posted an entry on Glen-L Hot Rod
Over the long weekend, we laminated three strips of fiberglass cloth on the chine and transom edges and ground them to a
-
Posted an entry on Glen-L Hot Rod
A strut pad was laminated from 3 layers of 1-1/2 ounce fiberglass mat
-
Posted an entry on Glen-L Hot Rod
Screw holes were puttied with Interlux Watertite YAV135
-
Posted an entry on Glen-L Hot Rod
On Friday night we fiberglassed the starboard bottom
-
Posted an entry on Glen-L Hot Rod
Fitting the port second bottom
-
Posted an entry on Glen-L Hot Rod
Both second bottom panels installed
-
Posted an entry on Glen-L Hot Rod
Port first bottom
-
Posted an entry on Glen-L Hot Rod
Starboard side
-
Posted an entry on Glen-L Hot Rod
Port side
-
Posted an entry on Glen-L Hot Rod
Prior to panel removal, keel, chine, batten, and butt block locations were traced with a pencil from inside the boat
-
Posted an entry on Glen-L Hot Rod
Port side first bottom ready to be epoxied
-
Posted an entry on Glen-L Hot Rod
Second bottom panels (1/4" marine grade plywood) were cut, scarfed and epoxied
-
Posted an entry on Glen-L Hot Rod
Butt blocks epoxied and clamped
-
Posted an entry on Glen-L Hot Rod
Plywood washers were used to increase the screw's clamping pressure
-
Posted an entry on Glen-L Hot Rod
Side planking was fastened with 1" #8 screws spaced 3" apart at the chine and 4" apart at the sheer
-
Posted an entry on Glen-L Hot Rod
Drainage limbers were cut into the rear battens
-
Posted an entry on Glen-L Hot Rod
The frame sides must be faired so that they don't project against the plywood planking
-
Posted an entry on Glen-L Hot Rod
Sheer fairing nearing completion
-
Posted an entry on Glen-L Hot Rod
Most of the first sheer lamination was faired away
-
Posted an entry on Glen-L Hot Rod
Since the Bill Of Materials call for a single layer of 1/4" sheeting for the sides, we'll be using 1/4" 5-Ply Meranti ma
-
Posted an entry on Glen-L Hot Rod
Here's a shot of the last side planking scarf joint being epoxied
-
Posted an entry on Glen-L Hot Rod
The strut was reinstalled and an 8' long piece of 1" round bar was slipped into it
-
Posted an entry on Glen-L Hot Rod
Two layers of 3/8" thick by 2" wide mahogany stock were laminated to the inside chine log surfaces
-
Posted an entry on Glen-L Hot Rod
A quick and accurate method of fairing the frames so they'll sit 1/8" below the battens involves running a router over t
-
Posted an entry on Glen-L Hot Rod
A fiberglass tube was inserted into the shaft hole